Section 232 tariffs back in play: what it means for CADs
LeBlanc signals interim deal would include Section 232 tariffs on steel, aluminum, autos, lumber. Origin claims and landed cost math need a second look.
The headline
Trade Minister Dominic LeBlanc told CBC this week that an interim U.S. deal would likely include Section 232 tariffs on steel, aluminum, autos and lumber, albeit at lower rates than the full tariff schedule. If that interim deal lands, it kicks off formal CUSMA review talks with the U.S. and Mexico.
That’s a planning problem for anyone importing those four commodity groups. Section 232 tariffs change the duty rate your broker files on the CAD. They change your landed cost. They change whether a CUSMA origin certificate is worth the paperwork or whether you skip the preference claim and just pay the tariff.
What Section 232 does to a CAD line
Section 232 is the U.S. trade law that lets the administration impose tariffs on national security grounds. When the U.S. applies Section 232 to Canadian goods, Canada typically mirrors it or negotiates an exemption. If the interim deal brings Section 232 back for steel, aluminum, autos and lumber shipped into Canada from the U.S., your broker files that additional duty on line 32 of the CAD alongside the base MFN or preferential rate.
The math:
- Base customs duty (MFN or CUSMA preferential, depending on origin)
- Section 232 tariff (new line, percentage TBD)
- Import GST at 5% of (adjusted value for duty + all duties)
If you’re importing U.S.-origin steel that currently clears at zero under CUSMA, and the interim deal adds a 10% Section 232 levy, your duty line goes from CAD 0 to CAD 10,000 on a CAD 100,000 shipment. Import GST base rises by the same CAD 10,000. Cash outlay at release (if you’re on release prior to payment with an RPP bond) stays the same day-of, but your monthly CARM Statement of Account will show the charge, and your RPP bond utilization ticks up.
Origin documentation matters more when tariff spreads widen
CUSMA preference claims have always been optional. If the tariff spread between MFN and preferential is narrow, some importers skip the certificate of origin and just pay the MFN rate to avoid the compliance load. When Section 232 tariffs enter the picture, that calculus flips.
Example: aluminum extrusions from a U.S. supplier. MFN rate might be 6%. CUSMA preferential is zero. Without Section 232, you’re deciding whether a certificate of origin is worth saving 6%. With a Section 232 tariff of 15% on top, the preference claim saves you 15%, and the certificate is suddenly worth the trouble.
Check your supplier origin documentation now. CUSMA certificates of origin can be prepared by the exporter, producer or importer. If you’ve been filing on importer-prepared certificates, make sure your records establish that the goods qualify: U.S. content, applicable CUSMA rule of origin for the HS classification, supplier declarations on file. CBSA’s origin verification group has four years to audit a CUSMA claim from the date of the CAD. If they verify and you can’t substantiate origin, you pay back the duty you saved, plus interest, and potentially an AMPS penalty if the documentation gap looks willful.
The HS classification question
Section 232 tariffs apply at the tariff-line level. If the interim deal lands, CBSA will publish a list of HS codes subject to the new levy. Aluminum sheet might be in; aluminum foil might be out. Auto parts at HS 8708 might be in; certain subheadings might have carve-outs.
If you’re importing any of the four commodity groups (steel, aluminum, autos, lumber), this is the time to confirm your broker is classifying correctly. An HS classification that’s close but wrong will cost you if it lands you on the Section 232 list when the correct code would have cleared it. The reverse is also a problem: if your broker is under-classifying to avoid a tariff, CBSA’s compliance officers will find it on audit, and you’ll pay penalties on top of the duty.
We run HS classification reviews as part of routine compliance work. Most misclassifications we catch are honest errors (supplier described the goods one way, actual use or material composition points to a different heading), but CBSA’s penalty framework under AMPS does not distinguish honest mistakes from intentional undervaluation once the error crosses certain thresholds. Get it right on the first CAD.
Timing uncertainty
LeBlanc’s comments signal intent, not implementation. There is no interim deal text yet. There is no tariff schedule, no effective date, no list of HS codes. That makes advance planning hard.
If you’re an importer with significant steel, aluminum, auto or lumber volume, the prudent move is to model the duty impact now. Pull your last quarter’s CAD data from the CARM Client Portal. Identify the HS codes that would be in scope. Run the math at a few tariff rate scenarios (5%, 10%, 15%). See what it does to your cost stack and your RPP bond utilization.
If the tariff lands and you’re not ready, you’ll be scrambling to explain a sudden landed cost spike to your finance team or your end customers. If you model it now and the tariff never materializes, you spent an afternoon on a spreadsheet. The downside is not symmetric.
The lumber file is different
Lumber is already subject to combined countervailing and anti-dumping duties under SIMA when certain softwood lumber products are imported from the U.S. SIMA duties are filed separately from customs duty on the CAD (line 34, duties under the Special Import Measures Act). If Section 232 tariffs stack on top of existing SIMA measures, U.S. softwood lumber could be carrying MFN customs duty + SIMA CVD + SIMA AD + Section 232. That’s four separate duty lines, all of which feed into the import GST base.
SIMA applies to subject goods: specific product definitions, specific countries of export, specific HS codes. If you’re importing lumber and you’re not sure whether your product is subject goods, that’s a question for your broker before the first shipment moves. SIMA penalties are steep, and the tribunal definitions are precise.
What to do
Three things:
-
Pull your import data for steel, aluminum, autos, lumber. HS codes, supplier countries, volumes, current duty rates. If you’re on CARM (you are), log into the Client Portal and export your CAD history. If your broker is filing for you and you don’t have portal access, ask them for a summary.
-
Confirm origin documentation is clean. If you’re claiming CUSMA preference on U.S. imports, make sure the certificates are on file, the origin rules are met, and the supplier can back it up. If you’re not claiming preference because the tariff spread was too narrow to bother, revisit that assumption with Section 232 in play.
-
Run the duty scenario. Pick a tariff rate (10% is a reasonable placeholder given LeBlanc’s comment about “lower rates”), apply it to your import base, see what the cash flow and landed cost impact looks like. If the number is material, talk to your broker about duty planning options: re-sourcing, tariff engineering, drawback if you’re re-exporting the finished goods.
The interim deal talks are early. The formal CUSMA review is further out. But the duty math doesn’t wait for the final text to be published. The importers who model this now will have options when the tariff schedule drops. The ones who wait will be paying whatever rate CBSA publishes and explaining the variance later.
If your duty exposure on these four commodity groups is significant, that’s the kind of scenario planning we run with clients every quarter. Get in touch.
Source: CSCB
Related insights
- CUSMA Review 2026: What Canadian Importers Should Watch
- Multi-Source Pharma Imports: Canadian Customs Clearance When Your API Comes from Three Countries
- U.S.-Taiwan Section 232 Deal: What Canadian Importers Should Watch
- El Paso Nearshoring Build and the Mexican CUSMA Inputs Entering Canada
- Crossing the Border Into Canada: How Shifting Trade Patterns Change Your Clearance Strategy